The Reporting Options selection criteria for this report allows you to specify:

Note: When calculating labor actuals, this report will include Adjustments based on the Work Date of the Adjustment -- no selection criteria is made available to alter this option.

 

Note regarding  Non-Billable Amount Suppression:

When charging Actuals to a non-billable project type, the hours values may be included in report output, however, any associated billable / revenue amounts will reflect $0.00.  This determination is based on the project type selected when saving the timesheet rather than the project's default project type.

Similarly, for any reports that use Assignment or Planned Work hours to calculate expected revenue, the billable / revenue amounts will also reflect $0.00 for project's having a non-billable default project type.