Type

The Type field is a dropdown list containing the types of predecessor relationships a task can have with another task.  The available options include the following (in each case, assume Task2 is being defined as dependent on Task1):

 

 

 

Example

To illustrate the various relationships, take the following example WBS where each of the sub-tasks are dependent on the parent Task 1 (having each of the 4 predecessor types).  

 

Task 1 is a task that ends on June 27, 2012 and each of the sub-tasks are defined as having a 2 day duration.  Because each of the sub-tasks are defined as having Task 1 as their predecessor, the date ranges for these sub-tasks are all derived (that is, you cannot manually manipulate them).  Making any changes to the Task 1 date range will cause the system to automatically recalculate the dates for the dependent sub-tasks.