Project Status
The Project Status field will contain the current status associated with a project. This status is defined on the project profile screen by the project manager. Various reports within Unanet allow you to search by project status.
The list of all project statuses available in your system is defined by the Administrator via the Admin Setup screens.
Each project status has an underlying Active indicator. Projects having a project status that is active are available for charging time and expense against. On the project profile screen, the project status dropdown list includes a display of the Active/Inactive indicator.
Note regarding preventing time/expense charges: Should you desire to prevent further time/expense charging to a project, simply updating the project status to an inactive value may not be enough. For example, if a user has saved time charges on their timesheet to a project and the project status is subsequently modified to an inactive project status, that time will remain on the timesheet. Further, the use can continue to add additional hours to any dates on that timesheet. When creating a new timesheet, that project will no longer appear, however, it will remain available on any timesheet it had been added to prior to the change of the project status to an inactive value.
If your goal is to prevent any further charging of time to a particular project, then, in addition to modifying its project status, you may also want to pursue one of the following 2 options:
1) Populate the Project Profile > Budget tab - Revised End Date field and check the "Enforce Project/Task Dates" check box. This will trigger the timesheet to validate and prevent the submittal of any additional time beyond the supplied Revised End Date.
2) Update the user's Assignment End Date for that project. This will trigger the timesheet to validate and prevent the submittal of any additional time beyond the supplied End Date.